Brad Schultz of the Department of Transportation has provided an update on the Highway 14 construction project in Richland Center:
Stage 2 work is nearing final completion. This week (May 28 & 29), new road base will be installed on Peebles Drive, restricting the intersection width, and concrete patches will begin from Bohmann Drive to State Highway 80.

Mainline paving starts June 1 on Bohmann Drive and continues east towards County O, aiming for completion by June 5th or 6th. Paving operations are 6 AM to 6 PM daily, and potential evening concrete sawing will be required for expansion joints.


A major traffic shift is still scheduled for early July. Michel’s (paving subcontractor) and H James (prime contractor) will coordinate driveway openings with all businesses and residents.

Please ensure safety by giving crews space and maintaining traffic flow – slowing to watch construction is extremely dangerous.

Adam Hess

Adam Hess has been involved in radio broadcasting since 1990, with many of those years spent on the air at WRCO FM in Richland Center. Currently, Adam hosts the Weekend Wake-up and Prime Mover Saturdays on WRCO FM, jumps in and helps out with news duties, handles Social Media duties for WRCO and WRCE, and is the Director of Technology at a Southwest Wisconsin School District. Reach him at adam.hess@civicmedia.us.

Civic Media App Icon

The Civic Media App

Put us in your pocket.

540 WAUK

100.3 FM - 101.1 FM - 540 AM

4201 Victory Ave. Racine, WI 53405

Studio: (262) 600-3600 (text or call)

Office: (262) 634-3311

info@waukradio.com


Facebook
Instagram
Twitter
Youtube
Bluesky
0:00